

後點擊查看之前
空間重新規劃一改二衛生間翻新 — 定製木紋櫃
西溫這個大型項目將一間浴室分隔成兩個功能齊全的獨立空間,每個都有獨立的管道、照明和通風系統。翻新採用了從地板到天花板的全牆瓷磚、定製木紋櫥櫃、現代天花線條的全新油漆,所有工程均通過了政府檢查。項目投資$57,000–$60,000,歷時9-11周,通過將浴室容量翻倍爲住宅增添了顯著的價值和實用性。
地點
West Vancouver期間
9-11周預算範圍
$57,000 - $60,000空間類型
獨立屋服務範圍
定製洗手櫃檯面更換全牆瓷磚水管工程燈光照明LED鏡子政府驗收通過牆體改動
挑戰
主要挑戰是有效地劃分現有空間,同時確保兩個衛生間符合現代標準和美學。
我們的解決方案
我們通過仔細規劃佈局和使用高質量材料來解決這一問題,確保兩個衛生間既時尚又實用。
Frequently Asked Questions
Frequently Asked Questions
- This project came in at $57,000–$60,000. The budget covered framing a new partition wall, full plumbing rough-in for a second bathroom (supply lines, drain, vent stack connection), electrical for a second light circuit and GFCI outlets, floor-to-ceiling tile in both bathrooms, custom vanity cabinets, all fixtures, and District of West Vancouver building and plumbing permits. Pricing varies based on existing rough-in proximity and finish level.
- Our West Vancouver two-bathroom split took 9–11 weeks from permit issuance to final inspection. A standard single-bathroom renovation typically runs 4–6 weeks. The additional time reflects the permit application lead time from the District of West Vancouver, the extra plumbing rough-in inspection stage, and the doubled tile and cabinet scope. Timeline can vary based on permit processing speed and material lead times.
- Yes. Splitting one bathroom into two requires a building permit (structural work — new partition wall) and a plumbing permit (new rough-in) from the District of West Vancouver. Electrical work for the new circuit may also require an electrical permit depending on scope. We pulled all required permits and coordinated all inspections on this project; all work passed government inspection before finishes were applied.




